03/12/2019
The EU Procurement thresholds for 2020-2021 have been released.
The new procurement thresholds, which will apply to the public sector from 1st January 2020, have been published. A short summary of the main thresholds is below:
Type of authority |
Type of contract |
|||
Works |
Supplies & services |
Light Touch Regime Services |
Concessions |
|
Central government bodies |
£4,733,252 (€5,350,000) |
£122,976 (€139,000) |
£663,540 (€750,000) |
£4,733,252 (€5,350,000) |
Sub-central authorities |
£4,733,252 (€5,350,000) |
£189,330 (€214,000) |
£663,540 (€750,000) |
£4,733,252 (€5,350,000) |
For reference:
These changes were published in Delegated Regulations of the Commission:
Public sector- works supplies and services thresholds (EU) 2019/1828
https://eur-lex.europa.eu/legal-content/EN/TXT/?qid=1574807901920&uri=CELEX:32019R1828
Concessions – (EU) 2019/1827
https://eur-lex.europa.eu/legal-content/EN/TXT/?qid=1574807901920&uri=CELEX:32019R1827
and conversion rates from Euro to Sterling are in Commission Communication 2019/C 370/01
https://eur-lex.europa.eu/legal-content/EN/TXT/?qid=1574808223493&uri=CELEX:52019XC1031(01)