18/02/2021

Drainage rights are crucial to the success of a development, yet these rights rarely hit the headlines as the commonest disputes tend to be around planning or title issues.  The recent case of Bernel Ltd v Canal & River Trust [2021] highlights how troublesome these rights can be when they are either not documented or there is insufficient proof that they exist.  The only option for the developer in this case was to claim it had pre-existing rights, but how easy is it to rely on either prescriptive rights or riparian rights to provide drainage for a development?

Facts of the case

Bernel Ltd (B) owned a site with planning permission to build nine houses which would need to drain onto neighbouring land owned by Canal & River Trust (the Trust).  B was unable to reach an agreement with the Trust for permission to do this.  An old pipe provided some drainage from the site onto the Trust’s land so B claimed that it had a right to drain on the basis that either:

  • the old pipe could be classified as a culverted natural watercourse, which would enable B to claim a riparian right to drain water into it; or
  • long usage of the pipe would enable B to claim a prescriptive right to drain onto the Trust’s land.

The High Court rejected B’s arguments.  Before a riparian right could be claimed, the court had to be satisfied that the existing drainage arrangements through the old pipe could be regarded as a natural watercourse.  On the facts, the court agreed with the Trust that there was no natural watercourse and no stream of water flowing in a defined channel.  There was insufficient evidence that significant amounts of surface water drained from the site onto the Trust’s land through this pipe.  In addition, reports showed that surface water percolated naturally through the ground, with some run-off onto the Trust’s land, but this was not through the old pipe.

B’s claim to a prescriptive right based on long usage of the pipe to discharge surface and foul water also failed as B was unable to provide sufficient proof of this.

Riparian rights

The court looked at previous authorities and considered that:

  • even if there are some periods of non-flow of water, this is still compatible with there being a natural watercourse;
  • where a dry channel is only filled during temporary flooding this is not a watercourse giving rise to riparian rights; and
  • whether a flow is temporary or otherwise is a question of fact for the court to decide.

The Trust was able to provide expert evidence on the nature of the site and the catchment area which led the court to decide that there was an insufficient regular flow through the old pipe to prove it was a watercourse.

Prescriptive rights

Although B was unable to provide the evidence required to prove it had a prescriptive right, the court went onto explain what it would have decided had B been able to do so.  This involved looking at the physical extent of the land which was originally one house and garden with an adjoining field (where the nine new houses were planned to be built).  The court took the view that even if a prescriptive right had been established, then that right would only extend to the house and garden and not the site as a whole.

This view was further supported by the radical change in the identity of the site from one house to nine houses on the larger adjoining field.  Therefore, B’s claim would have failed even with evidence of a prescriptive right to drain due to the change in identity and increased extent of the land claiming this right.

Practical points

Although the developer was unsuccessful in this particular instance, the High Court provided helpful guidance in relation to making a successful claim for either riparian or prescriptive rights.

Developers will be encouraged by the court’s view that had the old pipe been established as a watercourse, then draining surface water and treated foul water (in accordance with a permit from the Environment Agency) would permit “reasonable drainage operations” on the land.  The developer would then be able to rely on its riparian rights to do this.

It is always advisable to have drainage rights clearly documented, either in a deed of easement or in the deed transferring the title.  But bear in mind the court’s comments in this case, which apply equally to formal rights as well as those claimed by prescription; difficulties can still arise when the identity of land changes or there is a considerable increase in the use of the easement from that which was originally granted.  It will be interesting to see if future cases follow the same reasoning, but one lesson remains clear, developers should check drainage rights carefully to avoid buying land they may not be able to develop.

Our use of cookies

We use necessary cookies to make our site work. We'd also like to set optional analytics cookies to help us improve it. We won't set optional cookies unless you enable them. Using this tool will set a cookie on your device to remember your preferences. For more detailed information about the cookies we use, see our Cookies page.

Necessary cookies

Necessary cookies enable core functionality such as security, network management, and accessibility. You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics cookies

We'd like to set Google Analytics cookies to help us to improve our website by collection and reporting information on how you use it. The cookies collect information in a way that does not directly identify anyone.
For more information on how these cookies work, please see our Cookies page.